by darksun23c
From Starts & Stops:
According to Joe Pesaturo, more structural repairs are needed on the viaduct and service won't start till early fall.
Dang. Just dang. I was looking foward to riding up to Lechmere this summer.
Text of Article:
A tear for Lechmere
Cynthia of Cambridge recently asked a T bus driver when the train was due to start running again between Lechmere and Government Center on the Green Line. The driver said two years.
He was wrong about the length of the delay, which T officials said last week is now three to four months.
Background: The trolley line has been using bus shuttles between Lechmere and Government Center as the T completes a new $325 million underground route for the line after the dismantling of the elevated Green Line last year.
The change will allow for smoother transfer to subway service from North Station commuter rail. It was supposed to take a year, which meant completion sometime this month.
But the predicted yearlong project has hit some snags, namely more structural repairs than anticipated on the deteriorating viaduct that runs in front of the Museum of Science and up to Lechmere, said T officials.
MBTA spokesman Joe Pesaturo said the trolleys would now begin running sometime in the ''early fall," but he refused to be any more specific.
According to Joe Pesaturo, more structural repairs are needed on the viaduct and service won't start till early fall.
Dang. Just dang. I was looking foward to riding up to Lechmere this summer.
Text of Article:
A tear for Lechmere
Cynthia of Cambridge recently asked a T bus driver when the train was due to start running again between Lechmere and Government Center on the Green Line. The driver said two years.
He was wrong about the length of the delay, which T officials said last week is now three to four months.
Background: The trolley line has been using bus shuttles between Lechmere and Government Center as the T completes a new $325 million underground route for the line after the dismantling of the elevated Green Line last year.
The change will allow for smoother transfer to subway service from North Station commuter rail. It was supposed to take a year, which meant completion sometime this month.
But the predicted yearlong project has hit some snags, namely more structural repairs than anticipated on the deteriorating viaduct that runs in front of the Museum of Science and up to Lechmere, said T officials.
MBTA spokesman Joe Pesaturo said the trolleys would now begin running sometime in the ''early fall," but he refused to be any more specific.