The DCAC met back in Dec. Rail project update here:
https://www.dullestollroad.com/toll/dec ... ry-meeting
https://www.dullestollroad.com/sites/de ... 5_2019.pdf
There is discussion of several ongoing issues:
https://twitter.com/AdamTuss/status/1224717812507332608
https://www.dullestollroad.com/toll/dec ... ry-meeting
https://www.dullestollroad.com/sites/de ... 5_2019.pdf
There is discussion of several ongoing issues:
- Precast concrete panels
- Crossover hardware issue
- Ballast in the yard.
- Insulated joints.
- Cracks in precast panels in the buildings at the yard.
- Tight gauge in #8 switches
https://twitter.com/AdamTuss/status/1224717812507332608
NEW: Silver Line Phase 2 opening could slip to 2021. Latest project schedule has a substantial completion date of October 2020. But there’s months of testing after that, meaning that for the first time, 2021 is being talked about as a possible opening date