  by jaymac
 
Reportedly, the work going on around the northwest and southeast abutments of the Rte. 31 UGB is Extension-related and will provide access for bridge work.
Also, there is now a banner on the North Leominster garage announcing that it's open.
  by frrc
 
jaymac wrote:Reportedly, the work going on around the northwest and southeast abutments of the Rte. 31 UGB is Extension-related and will provide access for bridge work.
Also, there is now a banner on the North Leominster garage announcing that it's open.
RE: Leominster Garage, supposedly free parking for a while, then commuters will be charged to park there....
  by jaymac
 
Based on a ~0700/06-06-2014 drive-by and the presence of an excavator on the northeast embankment of the Bemis Street UGB along with an off-to-the side augur and a rebar cage, it looks like there may be new signals -- EB? -- going in for CPF-FG.
  by neman2
 
A lot of trackwork activity seen from a distance today (Saturday 6/07/14) between Ayer and Shirley. Tampers, ballast cars, regulators, rail heaters,hi-rail vehicles, excavators, and dump trucks. Without any public access in most of this area it's tough to say exactly what's going on, but it appears every weekend is an all-out effort.
  by johnpbarlow
 
Approximately mid-morning on Saturday 6/7/14, construction guys blocked part of Front St in Shirley to lift a large equipment cabinet into place along track 2 east of the T station parking lot. Looks like there will be a large signal gantry going in there judging by the huge concrete base already installed there. Work crews had track 1 barricaded between CP Slab City and CPF-AY and had Stop boards up on track 2 from Slab City to west wye at Ayer. Work was also going on at west end of siding and/or track 1 near MacPherson Rd at west end of Ayer. Too bad the Pan Am owned RoW isn't getting this same treatment! :wink:
  by matredsoxfan
 
Yesterday crews were testing gates and working near Route 117 crossing in Lincoln.
  by jaymac
 
Seen during a morning 06-11-2014 Fitchburg drive-through, small crew in PAR visi-vests and a large pile of sand at the southern abutment of the western River Street UGB and not 1 but 2 excavators on the northeast embankment of the Bemis Street UGB.
  by jaymac
 
Pre-0930/06-13-2014 drive-bys showed presumed surveying along 2 and east of the Rte. 31 UGB at Wachusett, traffic cones out at the western abutment of the western River Street UGB, and -- today -- only 1 excavator at the eastern embankment of the Bemis Street UGB.
  by jonnhrr
 
Out of curiosity, what does "UGB" stand for - from context it sounds like it refers to a RR bridge over the highway?

Google came up with "urban growth barrier" but that doesn't seem to apply here.

Jon
  by TrainManTy
 
jonnhrr wrote:Out of curiosity, what does "UGB" stand for - from context it sounds like it refers to a RR bridge over the highway?
Undergrade Bridge.
  by GP40MC1118
 
This weekend's work includes the cut-over of a new interlocking in Lincoln called CP-Hills.

CP-Hills is named after long retired, now deceased B&M Train Dispatcher Donald G.Hills. Don
was one of the best B&M TD's ever and a railfan to boot. Morning Sun put out a book of
his photos just prior to his passing.

251 operation continues for a few more weeks, then single track (261) with a new schedule
all the way to Tenny in Littleton to accommodate bridge rehab in Concord.

Dave
  by Mcoov
 
Wow, that's a lot of single tracking. Which side are they going to use? Eastbound or Westbound?
  by GP40MC1118
 
Not sure...I think No.2 Track gets done first.

D
  by Hoopyfrood
 
Does anyone have or know of the final plan for that bridge in Concord? It's needed work since the late 80s; I would imagine that nothing less than "tear it down in sections and rebuild it" is going to suffice.
  by B&M 1227
 
Which bridge is this in Concord? Is it the one that endured the truck strike a few years ago?