New switch east of Harold on mainline...

Discussion of the past and present operations of the Long Island Rail Road.

Moderator: Liquidcamphor

wintower
Posts: 378
Joined: Thu Jul 31, 2008 7:51 am

New switch east of Harold on mainline...

Post by wintower » Sun Jun 24, 2018 7:48 am

Anybody have information on the new switch, eastbound, east of the bridge over the SSYD loops? I believe it may have been installed last Thursday night into Friday morning or perhaps during the day on Friday.

adamj023
Posts: 296
Joined: Thu Apr 02, 2015 10:03 am

Re: New switch east of Harold on mainline...

Post by adamj023 » Sun Jun 24, 2018 3:14 pm

First time I have heard of it. I know the LIRR was fixing a switch in Jamaica and redoing others by year end. LIRR is testing the signals in Harold Yard but I wasn’t aware of any new switches installed there as of yet.

Backshophoss
Posts: 6318
Joined: Mon Mar 05, 2012 7:58 pm

Re: New switch east of Harold on mainline...

Post by Backshophoss » Sun Jun 24, 2018 6:14 pm

New switch could be part of the ESA project.
The Land of Enchantment is not Flyover country!

DaveBarraza
Posts: 298
Joined: Fri Aug 31, 2007 10:52 pm
Location: Out Past Ronkonkoma, NY

Re: New switch east of Harold on mainline...

Post by DaveBarraza » Sun Jun 24, 2018 6:37 pm

New alignment will allow for an eastbound ramp up from Grand Central to pop up between Tk.2 and Tk.4

Head-end View
Posts: 2656
Joined: Thu Mar 11, 2004 10:00 pm
Location: The second row on a SEPTA Silverliner V

Re: New switch east of Harold on mainline...

Post by Head-end View » Sun Jun 24, 2018 7:27 pm

There's been a lot of track realignment and relocating of switches on the eastbound tracks going on in that area for a long time now as part of ESA. It's hard to keep track of what they're doing when I only catch an M-3 with a clear front window maybe once a year to check it out. :(

Handtamp
Posts: 13
Joined: Tue Mar 24, 2015 7:32 pm
Location: Bottom of the Roster, better that way

Re: New switch east of Harold on mainline...

Post by Handtamp » Sun Jun 24, 2018 7:39 pm

Been watching both LIRR and Amtrak doing a lot of work around Harold lately.

I think the switch you are talking about has been there for a while. They just recently re-aligned the tracks to meet it.

There was a new switch, crossover really, being put in by the tower. It was on the new track that was built all the way to the south that had been not used for a while.

Lots of work this weekend.
"Back up the truck, its time to work"

wintower
Posts: 378
Joined: Thu Jul 31, 2008 7:51 am

Re: New switch east of Harold on mainline...

Post by wintower » Mon Jun 25, 2018 8:18 pm

The switch was not there when I passed by on Thursday afternoon and it comes in from the right of (south of) track 4. On Friday afternoon in Woodside track 4 was OOS and platforms were extended over it to allow access to trains stopped on track 2. (First four cars only...)

adamj023
Posts: 296
Joined: Thu Apr 02, 2015 10:03 am

Re: New switch east of Harold on mainline...

Post by adamj023 » Tue Jun 26, 2018 7:43 am

wintower wrote:The switch was not there when I passed by on Thursday afternoon and it comes in from the right of (south of) track 4. On Friday afternoon in Woodside track 4 was OOS and platforms were extended over it to allow access to trains stopped on track 2. (First four cars only...)
They did signal work too if I recall correctly over the weekend. Harold has been a work in progress for years. Never seems to end.

Harold has trains from Amtrak, NJ Transit and LIRR and is always active. While much of the work is for East Side Access, hopefully some of the work being done now will also benefit existing train lines.

jlr3266
Posts: 549
Joined: Thu Mar 18, 2004 7:32 am

Re: New switch east of Harold on mainline...

Post by jlr3266 » Tue Jun 26, 2018 11:00 pm

This is work by ESA Contract CH057D, a 3rd party trackwork contract primarily between 43rd St (over the loops) and 48th Street area to allow for the ESA tunnel connections and other improvements.

Return to “Long Island Rail Road (LIRR)”