Re: LIRR Mainline Third Track Project

 by Riverduckexpress ¦  Thu Mar 03, 2016 5:29 pm ¦  Forum: Long Island Rail Road (LIRR) ¦  Topic: LIRR Mainline Third Track Project ¦  Replies: 1245 ¦  Views: 287690

I don't think the MTA or the Governor's office have released detailed plans for this version yet. From The Island Now: Floral Park board passes anti-3rd track resolution Floral Park board passes anti-3rd track resolution Floral Park’s Village Board made its opposition to plans for a third track on t...

From the Hartford Courant: Plans Pitched For Thompsonville Train Station Plans Pitched For Thompsonville Train Station ENFIELD — Members of the town council will consider two preliminary design concepts for a future train station in Thompsonville and are expected to endorse one at a council meeting ...

Re: LIRR Mainline Third Track Project

 by Riverduckexpress ¦  Sat Feb 27, 2016 1:28 pm ¦  Forum: Long Island Rail Road (LIRR) ¦  Topic: LIRR Mainline Third Track Project ¦  Replies: 1245 ¦  Views: 287690

The central branch as badly needed as it is, will continue to be a sore subject. The biggest mistake came when the LIRR allowed the line from Flushing to Floral Park to be abandoned. The only direct East/West bypass of the Jamaica hub gone and having no chance to ever be restored as its all neighbo...

Re: #WeDeserveBetter

 by Riverduckexpress ¦  Thu Feb 25, 2016 12:09 pm ¦  Forum: Long Island Rail Road (LIRR) ¦  Topic: #WeDeserveBetter ¦  Replies: 85 ¦  Views: 14995

If the engineer got into a car accident and was almost killed on the way to work, why does the public need to know this??? Equipment problem is just fine thank you. It is an equipment problem because there is no one to operate the equipment and that is a problem. But "equipment problem" h...

Amtrak Boss Pledges Hartford Line Will Be Done On Time , from the Hartford Courant Amtrak Boss Pledges Hartford Line Will Be Done On Time There will be no more cost overruns or construction delays on the Hartford Line commuter rail project, the president of Amtrak said at a Senate hearing. Amtrak i...

Re: Acela Speeds

 by Riverduckexpress ¦  Wed Jan 20, 2016 7:57 pm ¦  Forum: Amtrak ¦  Topic: Acela Speeds ¦  Replies: 818 ¦  Views: 164825

I though the Harold Interlocking project was finished. Far from it. The MTA is building the Eastbound Bypass and Westbound Bypass tunnels. Right now, Amtrak trains traveling from the Hell Gate Line to East River Tunnels 1 and 2 have to cross over LIRR trains, but these grade-separated tunnels will ...

Re: First Cold Day Of The Year ....

 by Riverduckexpress ¦  Tue Jan 19, 2016 9:46 pm ¦  Forum: Long Island Rail Road (LIRR) ¦  Topic: First Cold Day Of The Year .... ¦  Replies: 20 ¦  Views: 4928

Don't forget two weeks ago there was a broken rail at Westbury. Coincidentally the same day Cuomo unveiled plans to finish the Main Line 3rd track. :-)

Re: CBTC Installation, Performance, Planning, and Progress

 by Riverduckexpress ¦  Tue Jan 19, 2016 8:30 pm ¦  Forum: NYCT MTA Subway, PATH and SIRT ¦  Topic: CBTC Installation, Performance, Planning, and Progress ¦  Replies: 51 ¦  Views: 29737

It's only going to stretch from 50 St/8 Av to around Union Turnpike. I guess at the moment the MTA doesn't see the need to cover anywhere else.
Here's the latest update from October (page 17)

Re: Acela Speeds

 by Riverduckexpress ¦  Tue Jan 19, 2016 7:19 pm ¦  Forum: Amtrak ¦  Topic: Acela Speeds ¦  Replies: 818 ¦  Views: 164825

Ironically, the MTA seems to partially blame Amtrak for delays with the Harold Bypass work, claiming that Amtrak is not providing support and outages when the MTA needs it to do work in the interlocking. MTA Dec 2015 Capital Program Oversight Committee Meeting (East Side Access discussion starts on ...

Re: Main 3rd track to be in Cuomo's 2016/17 state budget

 by Riverduckexpress ¦  Tue Jan 05, 2016 1:59 pm ¦  Forum: Long Island Rail Road (LIRR) ¦  Topic: LIRR Mainline Third Track Project ¦  Replies: 1245 ¦  Views: 287690

http://www.mta.info/press-release/lirr/lirr-undergo-major-improvements-expanding-along-main-line-floral-park-hicksville How are they going from 11.5 miles to 9.8? 11.5 miles - Distance from Queens Village to Hicksville 9.8 miles - Distance from Floral Park to Hicksville So apparently, any improveme...

Re: MTA LIRR Double Track Project - Ronkonkoma to Farmingdal

 by Riverduckexpress ¦  Tue Sep 01, 2015 6:09 pm ¦  Forum: Long Island Rail Road (LIRR) ¦  Topic: MTA LIRR Double Track Project - Ronkonkoma to Farmingdale ¦  Replies: 622 ¦  Views: 189693

To the posters saying they would rather reopen Republic than expand Pinelawn: It already is planned to be reopened: http://web.mta.info/capital/pdf/Board_2 ... df#page=80

Re: Post PM Rush Huntington Branch scheduling

 by Riverduckexpress ¦  Mon Aug 17, 2015 9:02 am ¦  Forum: Long Island Rail Road (LIRR) ¦  Topic: Post PM Rush Huntington Branch scheduling ¦  Replies: 8 ¦  Views: 3178

You're half right. The Babylon Branch does have higher ridership than the Huntington and Ronkonkoma Branches, but because the Babylon branch has so much service, trains to Babylon are on average less crowded than trains to Huntington and Ronkonkoma. Unfortunately, I don't really see things getting b...

LIRR Releases Mid-Suffolk Yard Environmental Assessment

 by Riverduckexpress ¦  Sat Aug 15, 2015 12:25 pm ¦  Forum: Long Island Rail Road (LIRR) ¦  Topic: LIRR Releases Mid-Suffolk Yard Environmental Assessment ¦  Replies: 1 ¦  Views: 1569

A couple of weeks ago the LIRR released a draft Environmental Assessment for the yard expansion in Ronkonkoma. They're still accepting public comments, until September 4th. Here are links: http://web.mta.info/lirr/midsuffolkyard/index.htm" onclick="window.open(this.href);return false; http...

Re: Greenport service

 by Riverduckexpress ¦  Mon Jul 13, 2015 8:28 am ¦  Forum: Long Island Rail Road (LIRR) ¦  Topic: East End Service: Greenport Scoot, Montauk Line, Etc. ¦  Replies: 541 ¦  Views: 108563

Is the current LIRR service to Greenport all rail or a combination rail and bus? Thanks. Bill O'Connell In the present, the LIRR's service is all rail. They generally only use buses when train service has to be suspended due to trackwork. However... on summer weekends, when the crowding on Montauk-...

Extra Trains For the Parade

 by Riverduckexpress ¦  Thu Jul 09, 2015 12:49 pm ¦  Forum: Long Island Rail Road (LIRR) ¦  Topic: Extra Trains For the Parade ¦  Replies: 0 ¦  Views: 1339

The MTA will run extra service tomorrow before and after the parade for the U.S. Women's Soccer Team. The schedule for eastbound trains after the parade looks mostly normal, but there's one an interesting westbound train: Leaving Farmingdale, and making all stops at Queens Village, then Jamaica. So ...