 #1617895  by daybeers
 
Jeff Smith wrote: Fri Mar 10, 2023 7:29 am So where are we at vis-a-vis number of sets delivered, testing progress, and acceptance?
6 trainsets have been delivered. 7" cant deficiency testing set for sometime this spring, with the goal of 6 trainsets for revenue service by the end of 2023. https://ngec.org/wp-content/uploads/202 ... uppert.pdf
 #1617907  by Jeff Smith
 
daybeers wrote: Fri Mar 10, 2023 10:13 pm
Jeff Smith wrote: Fri Mar 10, 2023 7:29 am So where are we at vis-a-vis number of sets delivered, testing progress, and acceptance?
6 trainsets have been delivered. 7" cant deficiency testing set for sometime this spring, with the goal of 6 trainsets for revenue service by the end of 2023. https://ngec.org/wp-content/uploads/202 ... uppert.pdf
Thanks "Mr. Beers"! New to me, great resource. Salient points:
New Acela Update
-Additional testing was conducted up to 5’ cant deficiency, up to 165 mph was completed in late CY22
-Testing up to 7” cant up to 165 mph targeted for the spring of CY23 following successful validation of the revised dynamic model
-6 Trainsets are expected to be commissioned before launch of revenue service
-Serial Trainsets TS03, TS04 and TS05 have been delivered to Penn Coach Yard
-TS06 and TS07 targeted for shipment in February and March 2023 respectively
-Start of revenue service, targeted for late CY2023.
 #1617950  by RandallW
 
The FRA requires testing beyond how a system will operate (this is why Brightline is testing their 125 MPH Orlando line at 130 MPH).
The NGEC standing is a matter of law (i.e., Congress created it). Can't get any more standing than that. (https://ngec.org/wp-content/uploads/202 ... ST-Act.pdf)
 #1619156  by Acela150
 
daybeers wrote: Fri Mar 10, 2023 10:13 pm
Jeff Smith wrote: Fri Mar 10, 2023 7:29 am So where are we at vis-a-vis number of sets delivered, testing progress, and acceptance?
6 trainsets have been delivered. 7" cant deficiency testing set for sometime this spring, with the goal of 6 trainsets for revenue service by the end of 2023. https://ngec.org/wp-content/uploads/202 ... uppert.pdf
6 sets have been delivered yes. However, 2 are prototype sets. Meaning little to no interiors are installed. These are for testing purposes. 1 went to TTCI and went back to Hornell, the other set is still in Philly. 3 production sets have been delivered and 2 of the 3 are in Philly. Not sure where the 3rd went.

I've heard some rumblings of more testing to take place in April.