Why is Wawa expansion so slow and costly??
Moderator: AlexC
-
- Posts: 82
- Joined: Wed Jul 05, 2017 6:31 pm
- Location: New England
Re: Why is Wawa expansion so slow and costly??
I went looking for information on this project and all I could find was this
http://septa.org/rebuilding/station/elwyn-wawa.html
Let me get this straight... SEPTA has budgeted $150.5 million to rehabilitate 3-miles of track, build a new stations and a 600-car parking deck? Maybe the budget also included additional EMU cars or work in the Media yard or work on the viaduct just to the west of Media? The price seem very high for a 3-mile extension of service.
If anyone has a link to more of the details please share it.
http://septa.org/rebuilding/station/elwyn-wawa.html
Let me get this straight... SEPTA has budgeted $150.5 million to rehabilitate 3-miles of track, build a new stations and a 600-car parking deck? Maybe the budget also included additional EMU cars or work in the Media yard or work on the viaduct just to the west of Media? The price seem very high for a 3-mile extension of service.
If anyone has a link to more of the details please share it.
-
- Posts: 143
- Joined: Fri Feb 27, 2009 12:51 pm
- Location: Media, PA
Re: Why is Wawa expansion so slow and costly??
*dusts off account after years of inactivity*Train60 wrote:I went looking for information on this project and all I could find was this
http://septa.org/rebuilding/station/elwyn-wawa.html
Let me get this straight... SEPTA has budgeted $150.5 million to rehabilitate 3-miles of track, build a new stations and a 600-car parking deck? Maybe the budget also included additional EMU cars or work in the Media yard or work on the viaduct just to the west of Media? The price seem very high for a 3-mile extension of service.
If anyone has a link to more of the details please share it.
Well, I'm no budgeting expert, nor am I a SEPTA apologist, but as a nearly lifelong Middletown Township resident, here's what I know needs to be done:
1) New track and ties - if you walk the Chester Creek rail trail, you may see how old the ties and rails are.
2) PTC signalling - the railroad will need to be equipped with this. FWIW, there appears to be an empty frame for a signal by the Lenni Road.
3) A new station - I'm no expert, but I imagine that this will be a challenging engineering feat. There doesn't appear to be enough room for a six hundred car garage on the the old station site https://www.google.com/maps/@39.9007756 ... a=!3m1!1e3 between where the creek bends suddenly. The terrain is also rather hilly; there will need to be some hard core landscaping to fit the garage. Not only that, garages are expensive - it is more expensive to build a garage of 600 spaces than the equivalent of 600 spaces on a flat surface lot.
4) They also once intended to build a new yard, since SEPTA was having storage problems when this project was first proposed. I don't know if that's still in the cards, though.
"I know nothing, nothing..." - Sgt. Schultz
-
- Posts: 574
- Joined: Thu Oct 08, 2009 1:17 am
- Location: Bristol, PA
Re: Why is Wawa expansion so slow and costly??
It was suggested some time ago to just get the service up and running, do everything minus the Wawa property and reopen the station at Glen Riddle which would nicely attract walk ups. Under that scenario, the trackwork and PTC could proceed, and service could be extended partially until they had funds and motivation for Wawa. Rome was built faster than this.
-
- Posts: 454
- Joined: Tue Jan 31, 2017 12:11 pm
Re: Why is Wawa expansion so slow and costly??
Renderings are up on SEPTA's rebuilding website:
http://septa.org/rebuilding/station/elwyn-wawa.html" onclick="window.open(this.href);return false;
http://septa.org/rebuilding/img/station ... wawa-1.jpg" onclick="window.open(this.href);return false;
http://septa.org/rebuilding/station/elwyn-wawa.html" onclick="window.open(this.href);return false;
http://septa.org/rebuilding/img/station ... wawa-1.jpg" onclick="window.open(this.href);return false;
-
- Posts: 1190
- Joined: Sun May 30, 2004 5:58 pm
- Location: Sabattus ME USA
Re: Why is Wawa expansion so slow and costly??
The drawings show 2 tracks at the station. I assume that the rest of the extension will remain single track for the time being.
Avatar Photo - P&W local from Gardner to Worcester at Morgan Rd., Hubbardston
-
- Posts: 454
- Joined: Tue Jan 31, 2017 12:11 pm
Re: Why is Wawa expansion so slow and costly??
I noticed that too, do you think that only one platform will be used for now, and then they'll add another track one day, or do you think they're gonna use a wye?jonnhrr wrote:The drawings show 2 tracks at the station. I assume that the rest of the extension will remain single track for the time being.
-
- Posts: 442
- Joined: Mon Jan 09, 2017 11:48 am
Re: Why is Wawa expansion so slow and costly??
Why would a wye be needed with only one platform indefinitely?mcgrath618 wrote:I noticed that too, do you think that only one platform will be used for now, and then they'll add another track one day, or do you think they're gonna use a wye?jonnhrr wrote:The drawings show 2 tracks at the station. I assume that the rest of the extension will remain single track for the time being.
-
- Posts: 725
- Joined: Fri Dec 08, 2006 11:30 pm
Re: Why is Wawa expansion so slow and costly??
It wouldn't. The station looks like it's going to be a two track station with an island platform. The line will obviously split into two tracks further up before Wawa and then merge back into one after and continue to West Chester.andrewjw wrote:Why would a wye be needed with only one platform indefinitely?mcgrath618 wrote:I noticed that too, do you think that only one platform will be used for now, and then they'll add another track one day, or do you think they're gonna use a wye?jonnhrr wrote:The drawings show 2 tracks at the station. I assume that the rest of the extension will remain single track for the time being.
When I first saw the renders, I thought the actual platform was going to be built over Baltimore Pike but it looks like it'll be just before it.
-
- Posts: 454
- Joined: Tue Jan 31, 2017 12:11 pm
Re: Why is Wawa expansion so slow and costly??
That's what I meant.ekt8750 wrote:It wouldn't. The station looks like it's going to be a two track station with an island platform. The line will obviously split into two tracks further up before Wawa and then merge back into one after and continue to West Chester.andrewjw wrote:Why would a wye be needed with only one platform indefinitely?mcgrath618 wrote:I noticed that too, do you think that only one platform will be used for now, and then they'll add another track one day, or do you think they're gonna use a wye?jonnhrr wrote:The drawings show 2 tracks at the station. I assume that the rest of the extension will remain single track for the time being.
When I first saw the renders, I thought the actual platform was going to be built over Baltimore Pike but it looks like it'll be just before it.
-
- Posts: 3369
- Joined: Sun Jul 22, 2007 5:11 pm
Re: Why is Wawa expansion so slow and costly??
are there economies of scale when it comes to track work? in other words, there is a fixed costs to getting the work site set up (and track designed) that can then support a larger amount of mileage? Perhaps the whole problem is that the extension is simply too small and as a result costs a heckuva lot more.
-
- Posts: 143
- Joined: Fri Feb 27, 2009 12:51 pm
- Location: Media, PA
Re: Why is Wawa expansion so slow and costly??
Here are a good amount of details, from a presentation given to MIddletown Township council in November.Train60 wrote:I went looking for information on this project and all I could find was this
http://septa.org/rebuilding/station/elwyn-wawa.html
If anyone has a link to more of the details please share it.
https://cloud.septa.org/s/LBvchGCL1QCATcT#pdfviewer
Highlights: the $150 million is going to the following:
- The station, the garage, and the bus loop
- Replacing the bridge over Route 1
- Replacing the two bridges over Chester Creek
- Replacing the bridge over Lungren Road. Good riddance to that one-lane underpass with poor visibility. It's Middletown's own "beep beep" bridge.
- Continuously welded rail
- Replacements of wire and catenary towers
- A new rail yard at Lenni
Fun tidbit: the expanded yard at Lenni will include a crew check-in office where parking at one end of the Chester Creek trail is located. I expect NIMBYs to complain about this.
"I know nothing, nothing..." - Sgt. Schultz
-
- Posts: 990
- Joined: Sun Jul 18, 2010 10:40 am
Re: Why is Wawa expansion so slow and costly??
New update on the Wawa project.
http://www.septa.org/rebuilding/news/ro ... -2019.html" onclick="window.open(this.href);return false;
http://www.septa.org/rebuilding/news/ro ... -2019.html" onclick="window.open(this.href);return false;
Starting at 8:00 p.m., Friday, February 8, crews will begin to remove the rail bridge spanning U.S. Route 1 as part of the Elwyn to Wawa Service Restoration Project. The replacement of the rail bridge is a critical phase of the restoration project to restore Media/Elwyn Line service from its current terminus at Elwyn Station to Wawa, Pa.
-
- Posts: 4009
- Joined: Thu Mar 11, 2004 10:45 pm
Re: Why is Wawa expansion so slow and costly??
One hopes they actually replace it. All this talk of 'critical phase', 'NIMBY' and fretting about costs, suggests this is is an awfully convenient way to deep-six the entire thing now and in the future.zebrasepta wrote:New update on the Wawa project.
http://www.septa.org/rebuilding/news/ro ... -2019.html" onclick="window.open(this.href);return false;Starting at 8:00 p.m., Friday, February 8, crews will begin to remove the rail bridge spanning U.S. Route 1 as part of the Elwyn to Wawa Service Restoration Project. The replacement of the rail bridge is a critical phase of the restoration project to restore Media/Elwyn Line service from its current terminus at Elwyn Station to Wawa, Pa.
"The bridge was removed, it'll cost too much to replace!"
(Not like SEPTA's ever done anything like that in the past...)
-
- Posts: 454
- Joined: Tue Jan 31, 2017 12:11 pm
Re: Why is Wawa expansion so slow and costly??
...Nasadowsk wrote:One hopes they actually replace it. All this talk of 'critical phase', 'NIMBY' and fretting about costs, suggests this is is an awfully convenient way to deep-six the entire thing now and in the future.zebrasepta wrote:New update on the Wawa project.
http://www.septa.org/rebuilding/news/ro ... -2019.html" onclick="window.open(this.href);return false;Starting at 8:00 p.m., Friday, February 8, crews will begin to remove the rail bridge spanning U.S. Route 1 as part of the Elwyn to Wawa Service Restoration Project. The replacement of the rail bridge is a critical phase of the restoration project to restore Media/Elwyn Line service from its current terminus at Elwyn Station to Wawa, Pa.
"The bridge was removed, it'll cost too much to replace!"
(Not like SEPTA's ever done anything like that in the past...)
They had to order a new bridge to be produced. They wouldn't drop the money on that and then not restore it.
They also wouldn't have done all the trackwork they've already done if their intention was just to sideline it.
-
- Posts: 574
- Joined: Thu Oct 08, 2009 1:17 am
- Location: Bristol, PA
Re: Why is Wawa expansion so slow and costly??
Don't be so sure. SEPTA doesn't care either way, to them it's all OPM (Other People's Money). They talk a good game when it comes to being a transit operator and helping the region, going "Green", etc, but at the end of the day they only answer to who signs their checks.