The East Side Access Project Discussion (ESA)

Discussion of the past and present operations of the Long Island Rail Road.

Moderator: Liquidcamphor

Herring
Posts: 49
Joined: Mon Oct 24, 2005 5:24 am

The East Side Access Project Discussion (ESA)

Post by Herring » Mon Jan 23, 2006 11:33 am

Here is the soltication for the Manhattan tunnel excavation portion of the ESA:

http://mta.info/nyct/procure/cc_solicitations.htm" onclick="window.open(this.href);return false; (click on CMOO9)

If you take a look at the MTA's ESA construction schedule, they are already two years behind schedule. So are there still believers (non-believers) that the ESA will never be built?

mark777
Posts: 465
Joined: Thu May 27, 2004 1:43 am
Location: somewhere near Redacted

ESA construction started??

Post by mark777 » Mon Aug 28, 2006 1:15 pm

I have noticed over the past few weeks that there are several cranes and bulldozers at the former site of the LIRR's Yard A at Sunnyside. If you look north of Amtrak's shops you'll see some of the work thats being done. It happens to be almost aligned with 21st street which is where the present bi-level tunnel under the east river is located (the lower level reserved for the LIRR, upper level being used by the NYCTA F line). Does anyone know if this has anything to do with the ESA construction?

Work Extra

Post by Work Extra » Mon Aug 28, 2006 4:16 pm

When is ESA going to be completed. I heard 2008 then 2010 Every time It keeps getting pushed back a few more years and a few million dollars.

mark777
Posts: 465
Joined: Thu May 27, 2004 1:43 am
Location: somewhere near Redacted

Post by mark777 » Mon Aug 28, 2006 4:38 pm

The last time I heard was now a completion date around 2013!!! Hope that it won't take as long as the Rosedale station to complete! :wink:

Work Extra

Post by Work Extra » Mon Aug 28, 2006 8:55 pm

HaHa. They were doing work on Rosedale Last Saturday.

Whats the hold up there?

mark777
Posts: 465
Joined: Thu May 27, 2004 1:43 am
Location: somewhere near Redacted

Post by mark777 » Mon Aug 28, 2006 9:34 pm

who knows? but the west end of the station took something like 2 years to complete, and the east end seems to be going the same way. Wouldn't doubt that it has to do with funds not being available to complete the work in a timely manner.

jlr3266
Posts: 549
Joined: Thu Mar 18, 2004 7:32 am

Post by jlr3266 » Tue Aug 29, 2006 7:30 am

You are seeing ESA Contract CQ028 which is digging a large open-cut and a mined crossing under Northern Blvd. The bored tunnel contracts in Manhattan and under Sunnyside Yard/Harold will be using this open-cut for access.

Contract CM009 has also been awarded, although it will be a while before any activity will be seen since the TBM's have to be ordered.

mark777
Posts: 465
Joined: Thu May 27, 2004 1:43 am
Location: somewhere near Redacted

Post by mark777 » Thu Aug 31, 2006 12:23 am

jlr3266:

It's nice to hear that work is has started. I'm sure that the work will be interesting in that it has to pass under the E, F, V, and R subway lines aswell as tunnel underneath the present F line under 21st street. I'm assuming that the cut and cover method won't be used for this construction.

Diverging Route
Posts: 1626
Joined: Sat Mar 13, 2004 3:35 pm

Post by Diverging Route » Thu Aug 31, 2006 6:48 am

mark777 wrote:The last time I heard was now a completion date around 2013!!! Hope that it won't take as long as the Rosedale station to complete! :wink:
There's a difference in the "company" that's doing these two projects.

Rosedale is being done by the LIRR.

The ESA is being done by LIRR's sister organization, MTA Capital Construction. It's run by the same folks that rebuilt the west side IRT after 9/11. They know how to get construction done... though they are of course constrained by availability of funding, regulations, permits, etc.
Enjoy Life!
Take the Diverging Route

jlr3266
Posts: 549
Joined: Thu Mar 18, 2004 7:32 am

Post by jlr3266 » Thu Aug 31, 2006 7:25 am

mark777 wrote:jlr3266:

It's nice to hear that work is has started. I'm sure that the work will be interesting in that it has to pass under the E, F, V, and R subway lines aswell as tunnel underneath the present F line under 21st street. I'm assuming that the cut and cover method won't be used for this construction.
C&C will only be used for the Plaza Interlocking/substation/vent facility and the approaches in Harold. Soft-ground TBMs under Sunnyside and most of Harold, and a short mined tunnel under Northern Blvd. TBM's and blasting for Manhattan.

themallard
Posts: 631
Joined: Fri Mar 19, 2004 6:45 pm
Location: New Jersey

LIRR Link Through Sunnyside On Track

Post by themallard » Fri Sep 01, 2006 12:02 pm

Work has been under way since 2001, but this summer, a bid was accepted for a company to dig the 3.5 miles of Manhattan tunnels needed to bring the LIRR deep under Grand Central Station, according to Beverly Dolinsky, executive director of the Permanent Citizens Advisory Committee to the Metropolitan Transportation Authority.
Some work in Queens is already under way as well: Upgrades are being made to the tracks near Woodside Avenue and 65th Street, and a large shaft completed in 2003 will be expanded underneath Northern Boulevard by the Sunnyside Railyards, according to the MTA.
Queens Chronicle

35dtmrs92
Posts: 505
Joined: Sun Nov 26, 2006 11:40 am
Location: New Haven, CT

Routing of ESA Plan

Post by 35dtmrs92 » Sun Mar 11, 2007 7:58 pm

As many know, the proposed East Side Access plan calls for a new station under the current Grand Central Terminal. I am curious why the tracks could not have connected to the current Metro-North tracks under Park Avenue leading to the existing terminal. I am thinking that grades or some other issue with the terrain of Manhattan had to do with it. Someone confirm this, please.

M1 9147
Posts: 1144
Joined: Thu Mar 11, 2004 10:47 pm
Location: Somewhere on the LIRR Railfanning

Post by M1 9147 » Sun Mar 11, 2007 8:24 pm

It has to do with third rail issues primarilly. Metro North uses under-running third rail where the shoes of each car goes underneath it, where as LIRR uses over-running third rail where the shoes go over it. Also to do a connection, there are 2 levels of Grand Central, and that would mean massive excavating of the existing tunnel(s) which would interfere with the levels of Metro North Services, rather than building a new level and station to the existing one where it totally makes sense. Similar work is supposed to be done at Penn when new platforms and and tunnels will be built to accomodate NJ Transit Trains right underneath 34th St.
Neil Feldman

Spartan Phalanx

Post by Spartan Phalanx » Sun Mar 11, 2007 9:53 pm

I wonder IF, sometime in the next twenty-years or so, we'll see NJT service to Grand Central. Of course, new tunnels and an even lower level would be needed, but is it possible? I think it's quite possible, after the LIRR is brought into the Lower Manhattan Financial District via Flatbush Avenue Terminal. All of Manhattan's important commercial areas, Financial District, Mid-Town and East Side should be rail-accessible by commuters from Long Island and Central/Northern New Jersey.

DutchRailnut
Posts: 22250
Joined: Thu Mar 11, 2004 8:02 pm
Location: released from Stalag 13

Post by DutchRailnut » Sun Mar 11, 2007 9:56 pm

not gone happen.
If Conductors are in charge, why are they promoted to be Engineer???

Retired Triebfahrzeugführer. I am not a moderator.