Post by PlaneLoverA380 » Mon Dec 17, 2018 8:09 am

LIRR has released renderings of a 3-track Mineola.
You do not have the required permissions to view the files attached to this post.
As you leave the train, please step over the gap between the train and the platform

https://m.youtube.com/c/RailstormersRailAviation - My channel, I upload my railfanning catches here.

LB
Posts: 482
Joined: Fri Sep 07, 2007 12:13 pm
Location: Callaway, MD

Re: LIRR Mainline Third Track Project

Post by LB » Tue Dec 18, 2018 7:19 am

I saw some work going on at Urban Ave, New Cassel in late November. Is that the first grade crossing to get eliminated?

User avatar
PlaneLoverA380
Posts: 103
Joined: Wed May 02, 2018 2:04 pm
Location: Railfanning at Mineola

Re: LIRR Mainline Third Track Project

Post by PlaneLoverA380 » Tue Dec 18, 2018 10:46 am

That is one of the crossings they were planning to eliminate. If the third track is being built from Hicksville west, then I would expect that one to be the first to go. Wonder if they’re going to keep that ped crossing at Mineola.
As you leave the train, please step over the gap between the train and the platform

https://m.youtube.com/c/RailstormersRailAviation - My channel, I upload my railfanning catches here.

User avatar
MattAmity90
Posts: 888
Joined: Sat Apr 21, 2012 4:46 pm
Location: Easton, PA

Re: LIRR Mainline Third Track Project

Post by MattAmity90 » Tue Dec 18, 2018 1:21 pm

PlaneLoverA380 wrote:That is one of the crossings they were planning to eliminate. If the third track is being built from Hicksville west, then I would expect that one to be the first to go. Wonder if they’re going to keep that ped crossing at Mineola.
The project states that ALL grade crossings will either be eliminated or converted to dead ends, which means that both pedestrian and vehicular crossings. In fact, Urban Avenue is not the only one seeing activity, they are doing work at Covert Avenue. Those are the first two crossings that will be eliminated because Urban Avenue is the first crossing West of Hicksville, and Covert Avenue is the first crossing East of Floral Park.

Carle Place's EB platform had its Western half demolished (rear 6 cars of an EB train), and work has begun on the embankment as construction vehicles have installed corrugated columns to add Earth or a concrete wall. Bulldozers have been going over the area where the platform once existed to level out the soil to the same level as the tracks (and placement of the third track), and LIPA vehicles and LIRR workers have constructed new bundle-cable power lines South of the ROW. All along the ROW Jersey dividers with fencing have been placed on the South side of the ROW as well.
This station is Babylon, this is the train to Penn Station. Stopping at: Lindenhurst, Copiague, Amityville, Massapequa Park, Massapequa, Seaford, Wantagh, Bellmore, Merrick, Freeport, Baldwin, Rockville Centre, Lynbrook, Valley Stream, Jamaica, Kew Gardens, Forest Hills, Woodside, Penn Station.

User avatar
PlaneLoverA380
Posts: 103
Joined: Wed May 02, 2018 2:04 pm
Location: Railfanning at Mineola

Re: LIRR Mainline Third Track Project

Post by PlaneLoverA380 » Tue Dec 18, 2018 2:06 pm

So will the ped crossing be built into a bridge? :P I’m going to miss those horn blasts while railfanning.
As you leave the train, please step over the gap between the train and the platform

https://m.youtube.com/c/RailstormersRailAviation - My channel, I upload my railfanning catches here.

Head-end View
Posts: 2659
Joined: Thu Mar 11, 2004 10:00 pm
Location: The second row on a SEPTA Silverliner V

Re: LIRR Mainline Third Track Project

Post by Head-end View » Tue Dec 18, 2018 8:39 pm

I'm guessing the Mineola Main St. crossing will be eliminated by dead-ending that street on both sides; which is unfortunate in my opinion. And I predict it will be replaced by a pedestrian overpass that will serve both Main St. and the current ped crossing. :(

User avatar
PlaneLoverA380
Posts: 103
Joined: Wed May 02, 2018 2:04 pm
Location: Railfanning at Mineola

Re: LIRR Mainline Third Track Project

Post by PlaneLoverA380 » Tue Dec 18, 2018 8:50 pm

Yeugh.... I’m shuddering thinking of that. On a *slightly* better note, at least it will be good for railfanning... if railfanning is ever worth it anymore. *sheds tear*
As you leave the train, please step over the gap between the train and the platform

https://m.youtube.com/c/RailstormersRailAviation - My channel, I upload my railfanning catches here.

Head-end View
Posts: 2659
Joined: Thu Mar 11, 2004 10:00 pm
Location: The second row on a SEPTA Silverliner V

Re: LIRR Mainline Third Track Project

Post by Head-end View » Tue Dec 18, 2018 9:45 pm

Railfanning has existed for generations. When steam loco's were phased out people predicted no one would ever find those bland looking diesels interesting........... So I don't think we have to worry about any imminent demise of railfanning. LOL Only front-window viewing is on the way out unless you ride SEPTA Silverliner V's regularly, which regrettably I'm not able to.

scopelliti
Posts: 546
Joined: Thu Mar 11, 2004 10:35 pm
Location: Big Flats, NY

Re: LIRR Mainline Third Track Project

Post by scopelliti » Tue Dec 18, 2018 10:21 pm

Head-end View wrote:I'm guessing the Mineola Main St. crossing will be eliminated by dead-ending that street on both sides; which is unfortunate in my opinion. And I predict it will be replaced by a pedestrian overpass that will serve both Main St. and the current ped crossing. :(
Yes I read that Main Street crossing will be eliminated by dead-ending on both sides. Not sure about the pedestrian bridge. Earlier there was a link to the LIRR project site. That info kind of moved around .. I would check http://lirrexpansion.com/ for more info.

Mineola Blvd will go under the tracks. Nassau Tower is toast :( Spent a lot of time in the 1960s railfanning right there...
Pat

User avatar
PlaneLoverA380
Posts: 103
Joined: Wed May 02, 2018 2:04 pm
Location: Railfanning at Mineola

Re: LIRR Mainline Third Track Project

Post by PlaneLoverA380 » Tue Dec 18, 2018 10:25 pm

I heard that a new museum is coming to Mineola, and they will save the Tower. Just hope...
As you leave the train, please step over the gap between the train and the platform

https://m.youtube.com/c/RailstormersRailAviation - My channel, I upload my railfanning catches here.

Norton
Posts: 85
Joined: Sun Nov 22, 2009 1:39 pm

Re: LIRR Mainline Third Track Project

Post by Norton » Wed Dec 19, 2018 10:02 am

scopelliti wrote:
Mineola Blvd will go under the tracks.
Negative. The Mineola Blvd. bridge will remain more or less as is, with the tracks passing under the roadway.

User avatar
MattAmity90
Posts: 888
Joined: Sat Apr 21, 2012 4:46 pm
Location: Easton, PA

Re: LIRR Mainline Third Track Project

Post by MattAmity90 » Wed Dec 19, 2018 3:36 pm

What the turnout will be after the project is completed:

1.) Covert Avenue, New Hyde Park Road, Willis Avenue (Main Line), School Street, and Urban Avenue will be eliminated with the road going under the tracks.
2.) 12th Street, and Main Street will be closed and converted into dead ends.
3.) Reconfiguration of NASSAU Interlocking and DIVIDE Interlocking.
4.) What is currently Track 2 will be renamed Track 3 and be the express track. All local tracks are numbered the lowest.
5.) Replacement of Dunton Avenue, Nassau Boulevard, Glen Cove Road, and Cherry Lane bridges.
6.) The Willis Avenue grade crossing (Oyster Bay) will still exist, but it will be above a tunnel in which the traffic will go through.
7.) Pedestrian crossing will be converted into a pedestrian overpass.
8.) New Hyde Park and Merillon Avenue stations will be lengthened from 10 to 12 car lengths.
9.) New Hyde Park station will be moved slightly further West.
10.) New Hyde Park, Merillon Avenue, Mineola, Carle Place, and Westbury will see their ADA accessibilities replaced and upgraded to improve it (elevators).
11.) All platforms will be rehabilitated with ASIMS.

I'm hoping that if unfortunately and just in case they can't save NASSAU tower, they move the structure to the triangular section where the Oyster Bay Branch diverts North from the Main Line.
This station is Babylon, this is the train to Penn Station. Stopping at: Lindenhurst, Copiague, Amityville, Massapequa Park, Massapequa, Seaford, Wantagh, Bellmore, Merrick, Freeport, Baldwin, Rockville Centre, Lynbrook, Valley Stream, Jamaica, Kew Gardens, Forest Hills, Woodside, Penn Station.

Head-end View
Posts: 2659
Joined: Thu Mar 11, 2004 10:00 pm
Location: The second row on a SEPTA Silverliner V

Re: LIRR Mainline Third Track Project

Post by Head-end View » Wed Dec 19, 2018 8:33 pm

Matt, are you sure about the track numbering scheme in item #4? LIRR doesn't normally number tracks that way. At least not in the 4-track area. Normally the inside tracks are 1-2. And the outside tracks are 3-4. Are they going to have a separate numbering scheme just for the stretch from Floral Park to Hicksville? :(

LB
Posts: 482
Joined: Fri Sep 07, 2007 12:13 pm
Location: Callaway, MD

Re: LIRR Mainline Third Track Project

Post by LB » Thu Dec 20, 2018 7:41 am

The Meadowbrook Pkwy bridge is only two tracks, .... what's the plan there?

Norton
Posts: 85
Joined: Sun Nov 22, 2009 1:39 pm

Re: LIRR Mainline Third Track Project

Post by Norton » Thu Dec 20, 2018 11:05 am

According to this document http://lirrexpansion.com/wp-content/upl ... gnment.pdf" onclick="window.open(this.href);return false;, a new single-track bridge will be built to the south of the existing bridge.