NJT won't meet PTC Deadline

Postby blockline4180 » Wed Jun 27, 2018 2:53 pm

New Jersey Transit will not meet the December 31 deadline to have a crucial safety system known as Positive Train Control up and running, Executive Director Kevin Corbett told NBC News 4 New York on Tuesday.

Instead, the third-largest commuter railroad in the nation says it will need an extension of up to two years, as provided for under law — assuming NJT can convince regulators to grant it.



https://www.nbcphiladelphia.com/news/local/NJ-Transit-PTC-Deadline-486663441.html
~Steve Pellettiere
Co-Moderator: DL&W/Erie/EL Forum
"Each of us makes his own weather, determines the color of the skies in the emotional universe which he inhabits."
User avatar
blockline4180
 
Posts: 5523
Joined: Mon Aug 07, 2006 10:58 am
Location: NJ and me, Broke Together!

Re: NJT won't meet PTC Deadline

Postby DutchRailnut » Wed Jun 27, 2018 5:44 pm

a waiver is granted if a reasonable effort is made to meet the goal,
having only 8% of trains equipped and 0% of track is not a reasonable effort.
If Conductors are in charge, why are they promoted to be Engineer???

Retired Triebfahrzeugführer. I am not a moderator.
User avatar
DutchRailnut
 
Posts: 21929
Joined: Thu Mar 11, 2004 8:02 pm
Location: released from Stalag 13

Re: NJT won't meet PTC Deadline

Postby trainster78 » Wed Jun 27, 2018 6:33 pm

Yea well that was from March, apparently its gone "ludicrous speed" since then.
trainster78
 
Posts: 158
Joined: Wed Jun 28, 2017 11:59 am
Location: Red Bank

Re: NJT won't meet PTC Deadline

Postby SecaucusJunction » Wed Jun 27, 2018 10:36 pm

They’ve only had 9 years to sit on their hands thinking about it...
I think it may be possible that NJ Transit might not be the perfect, infallible organization that most people assume it is.
SecaucusJunction
 
Posts: 3064
Joined: Mon Apr 26, 2004 9:40 pm
Location: NS Watchdog

Re: NJT won't meet PTC Deadline

Postby blockline4180 » Thu Jun 28, 2018 8:25 am

SecaucusJunction wrote:They’ve only had 9 years to sit on their hands thinking about it...


Well, yes, what would you expect?? lol
~Steve Pellettiere
Co-Moderator: DL&W/Erie/EL Forum
"Each of us makes his own weather, determines the color of the skies in the emotional universe which he inhabits."
User avatar
blockline4180
 
Posts: 5523
Joined: Mon Aug 07, 2006 10:58 am
Location: NJ and me, Broke Together!

Re: NJT won't meet PTC Deadline

Postby EuroStar » Thu Jun 28, 2018 9:08 am

This is not really news. It is also of no consequence whatsoever. The FRA has no choice, but to squint and give NJT the two year extension. Politically and practically any other action is impossible. If NJT were blatantly ignoring the deadline, then yeah, they would not get the extension, but whatever NJT is doing will count as good enough effort and they will get the two extra years.

My educated guess is that priority is given to the equipment in electrical territory because it runs on tracks owned by Amtrak, so the NEC, the M&E to Dover/MSU and the Coast Line to Long Branch will get done by the deadline. The rest will be in various stages, most likely with with hardware placed along the tracks, but untested and maybe even not wired when December 31st rolls around.
EuroStar
 
Posts: 588
Joined: Fri Oct 19, 2012 8:26 pm
Location: Middle of Nowhere

Re: NJT won't meet PTC Deadline

Postby DutchRailnut » Thu Jun 28, 2018 12:25 pm

FRA is already saying NJT does not qualify for extension.
https://www.progressiverailroading.com/ ... ion--55001
If Conductors are in charge, why are they promoted to be Engineer???

Retired Triebfahrzeugführer. I am not a moderator.
User avatar
DutchRailnut
 
Posts: 21929
Joined: Thu Mar 11, 2004 8:02 pm
Location: released from Stalag 13

Re: NJT won't meet PTC Deadline

Postby Backshophoss » Thu Jun 28, 2018 8:49 pm

Part of the reason is that former gov Christe kept taking away the needed cash to do the job right from the beginning...... :(
Backshophoss
 
Posts: 5697
Joined: Mon Mar 05, 2012 7:58 pm

Re: NJT won't meet PTC Deadline

Postby R&DB » Fri Jun 29, 2018 4:57 am

DutchRailnut » Thu Jun 28, 2018 1:25 pm

FRA is already saying NJT does not qualify for extension.

So what are they going to do, shut down NJT?
Harry
User avatar
R&DB
 
Posts: 501
Joined: Thu Jan 16, 2014 12:55 pm
Location: Sou.Sec. MP 53.6

Re: NJT won't meet PTC Deadline

Postby EuroStar » Fri Jun 29, 2018 8:12 am

R&DB wrote:
FRA is already saying NJT does not qualify for extension.

So what are they going to do, shut down NJT?


And that is exactly my point. It does not matter what the FRA says now, come December they will squint their eyes and give the two year extension. The only way NJT can shoot itself in the foot is by having another deadly accident similar to the Hoboken crash. As long as they avoid that they will be fine.
EuroStar
 
Posts: 588
Joined: Fri Oct 19, 2012 8:26 pm
Location: Middle of Nowhere

Re: NJT won't meet PTC Deadline

Postby SecaucusJunction » Fri Jun 29, 2018 8:30 am

So NJT will do just enough to get an extension, then do nothing for 2 years and cry in 2021 that they can't get it done.



The railroads already got one PTC inspection and are now hoping for more. The truckers didn't get this when campaigning against ELD's...
I think it may be possible that NJ Transit might not be the perfect, infallible organization that most people assume it is.
SecaucusJunction
 
Posts: 3064
Joined: Mon Apr 26, 2004 9:40 pm
Location: NS Watchdog

Re: NJT won't meet PTC Deadline

Postby DutchRailnut » Fri Jun 29, 2018 11:26 am

Amtrak has also stated that in 2019 no trains without PTC will be allowed to run on their property .
If Conductors are in charge, why are they promoted to be Engineer???

Retired Triebfahrzeugführer. I am not a moderator.
User avatar
DutchRailnut
 
Posts: 21929
Joined: Thu Mar 11, 2004 8:02 pm
Location: released from Stalag 13

Re: NJT won't meet PTC Deadline

Postby EuroStar » Fri Jun 29, 2018 2:52 pm

DutchRailnut wrote:Amtrak has also stated that in 2019 no trains without PTC will be allowed to run on their property .

Yes, Amtrak said that and they as opposed to FRA will not cut NJT any slack due to liability. But as I said in my previous comment, NJT will get PTC working on the equipment that runs into NYP (the electrical equipment) in time, so they will be fine. It is the rest of the system that won't be ready by January 1, 2019.
EuroStar
 
Posts: 588
Joined: Fri Oct 19, 2012 8:26 pm
Location: Middle of Nowhere

Re: NJT won't meet PTC Deadline

Postby Backshophoss » Fri Jun 29, 2018 6:23 pm

That should also include the Atlantic City service trains into 30th st station in Phila.
Backshophoss
 
Posts: 5697
Joined: Mon Mar 05, 2012 7:58 pm

Re: NJT won't meet PTC Deadline

Postby Ken W2KB » Fri Jun 29, 2018 9:42 pm

EuroStar wrote:
DutchRailnut wrote:Amtrak has also stated that in 2019 no trains without PTC will be allowed to run on their property .

Yes, Amtrak said that and they as opposed to FRA will not cut NJT any slack due to liability. But as I said in my previous comment, NJT will get PTC working on the equipment that runs into NYP (the electrical equipment) in time, so they will be fine. It is the rest of the system that won't be ready by January 1, 2019.


Besides the NEC trains, all Raritan Valley Line and NJ Coast Line trains run in part on Amtrak’s NEC, plus the Midtown Direct service. A substantial portion of NJT equipment will need PTC.
~Ken :: Fairmont ex-UP/MP C436 MT-14M1 ::
Black River Railroad Historical Trust :: [/url]
User avatar
Ken W2KB
 
Posts: 5722
Joined: Thu Mar 11, 2004 9:27 pm
Location: Lebanon Township, Hunterdon County, New Jersey & Tiverton, RI USA