NJT won't meet PTC Deadline

Discussion related to New Jersey Transit rail and light rail operations.

Moderators: Tadman, Kaback9, nick11a, ACeInTheHole

Re: NJT won't meet PTC Deadline

Postby andrewjw » Wed Oct 03, 2018 9:53 am

Yeah, it looks like this:

Code: Select all
`-------->-------
        /
-------<---------


where < and > are switches and the bottom track is the southbound local track on the NEC, which is going southwest=leftward.

I asked the engineer when I was on board in the past few days and he said that the current plan is that they will not install PTC equipment on the Princeton branch trackage - though the Arrow MUs running on the branch will be PTC-capable.
andrewjw
 
Posts: 309
Joined: Mon Jan 09, 2017 11:48 am

Re: NJT won't meet PTC Deadline

Postby Graeme Salt » Wed Oct 03, 2018 1:01 pm

Sort of relevant to this thread, but apologies if deemed an inappropriate question - can anyone advise whether (i) the top'n'tailing of passenger sets with two engines in lieu of cab cars oos for PTC equipment installation, and (ii) the use of non-revenue locomotives, are still going on? Or have the recent service reductions and temporary closure of the AC line removed the need?
Graeme Salt
 
Posts: 21
Joined: Thu Oct 29, 2015 2:40 pm

Re: NJT won't meet PTC Deadline

Postby EuroStar » Mon Nov 19, 2018 9:02 am

EuroStar wrote:As per NJT board presentation as of September 7:
131 pieces of equipment (read cab cars and engines) have PTC gear installed with 151 left to go
19 poles remain out of 111
27 antennas remain out of 111
21 wayside units remain out of 119
44 people need training out of 1305

PTC test area has been extended to between Denville andSummit (it had been between Denville and Morristown).

As per the October board meeting the status as of October 5th was:
165 pieces of equipment have PTC with 117 left to go
4 poles remain out of 111
18 antennas remain out of 111
9 wayside units remain out of 119
1 person left to train out of 1305
EuroStar
 
Posts: 573
Joined: Fri Oct 19, 2012 8:26 pm
Location: Middle of Nowhere

Re: NJT won't meet PTC Deadline

Postby lensovet » Tue Nov 20, 2018 6:56 pm

that's not too bad though i suspect more cutbacks are going to be needed in january given how many units are still not equipped.
Paul Borokhov

Last RRPicArch addition – NJ Railfan.

NJT RailCalifornia commuter (mod)
User avatar
lensovet
 
Posts: 1004
Joined: Thu Jul 20, 2006 7:30 pm
Location: SF Bay Area, CA

Re: NJT won't meet PTC Deadline

Postby andrewjw » Tue Nov 20, 2018 7:57 pm

They equipped 34 more in September. Suppose they do the same in October, November, and December, then they will be down from 117 left to go, to 15 left to go. So they have a bit of leeway - so long as they have fewer than 34 left to go in January they will not need to make any more service cuts.
andrewjw
 
Posts: 309
Joined: Mon Jan 09, 2017 11:48 am

Re: NJT won't meet PTC Deadline

Postby EuroStar » Wed Nov 21, 2018 3:58 pm

EuroStar wrote:
EuroStar wrote:As per NJT board presentation as of September 7:
131 pieces of equipment (read cab cars and engines) have PTC gear installed with 151 left to go
19 poles remain out of 111
27 antennas remain out of 111
21 wayside units remain out of 119
44 people need training out of 1305

PTC test area has been extended to between Denville andSummit (it had been between Denville and Morristown).

As per the October board meeting the status as of October 5th was:
165 pieces of equipment have PTC with 117 left to go
4 poles remain out of 111
18 antennas remain out of 111
9 wayside units remain out of 119
1 person left to train out of 1305


As of last week:
221 pieces of equipment have PTC with 61 left to go
5 antennas remain out of 111

I believe that these came out of the November board meeting and I have no official public source for these.
EuroStar
 
Posts: 573
Joined: Fri Oct 19, 2012 8:26 pm
Location: Middle of Nowhere

Re: NJT won't meet PTC Deadline

Postby Defiant » Tue Nov 27, 2018 5:16 pm

So will NJT meet the PTC deadline or not? If all the equipment has PTC equipment installed? What about the actual railroad tracks?
Defiant
 
Posts: 142
Joined: Fri Sep 17, 2010 10:00 am

Re: NJT won't meet PTC Deadline

Postby andrewjw » Tue Nov 27, 2018 5:49 pm

Defiant wrote:So will NJT meet the PTC deadline or not? If all the equipment has PTC equipment installed? What about the actual railroad tracks?

The wayside units, antennas, and poles are the "railroad track" equipment. The rails themselves do not need to be altered.

It looks like they will make the deadline. As of Jan 1 they will be able to have all of the equipment which does not have PTC installed be out of service without having to further cut schedules.
andrewjw
 
Posts: 309
Joined: Mon Jan 09, 2017 11:48 am

Re: NJT won't meet PTC Deadline

Postby Defiant » Thu Dec 06, 2018 12:28 pm

andrewjw wrote:
Defiant wrote:So will NJT meet the PTC deadline or not? If all the equipment has PTC equipment installed? What about the actual railroad tracks?

The wayside units, antennas, and poles are the "railroad track" equipment. The rails themselves do not need to be altered.

It looks like they will make the deadline. As of Jan 1 they will be able to have all of the equipment which does not have PTC installed be out of service without having to further cut schedules.



OK, but will they actually activate PTC system by 12/31/2018? When PATH actually turned on the system earlier this year, it was at first a disaster and caused a lot of delays... I shudder to think what would happen on NJT. Any idea what their plans for actually turning on and using the system are?
Defiant
 