Postby JamesRR » Fri Apr 28, 2017 4:04 pm

Does anyone know what's happening on the northernmost Shuttle track at the GC Station platform? It's all boarded up.

Is a new connection being made to the new Vanderbilt project going on above ground?
User avatar
JamesRR
 
Posts: 281
Joined: Thu Jul 10, 2008 3:31 pm

Re: Grand Central Station - Shuttle Platform Work

Postby Allan » Sat Apr 29, 2017 6:01 pm

JamesRR wrote:Does anyone know what's happening on the northernmost Shuttle track at the GC Station platform? It's all boarded up.

Is a new connection being made to the new Vanderbilt project going on above ground?


It is related to sidewalk work being done above for 1 Vanderbilt and is probably part of the connection work being done on the Mezzanine just above track 4.
Allan
 
Posts: 391
Joined: Mon Oct 18, 2004 7:10 am
Location: Bronx, NY

Re: Grand Central Station - Shuttle Platform Work

Postby Allan » Wed Aug 02, 2017 1:27 pm

Sidewalk work has been completed and as of 8/1/17, track 4 is back in operation.
Allan
 
Posts: 391
Joined: Mon Oct 18, 2004 7:10 am
Location: Bronx, NY


Return to NYC MTA Subway and Rail, PATH and SIRT

Who is online

Users browsing this forum: No registered users and 1 guest