Original NH Catenary Replacement Progress

Discussion relating to the operations of MTA MetroNorth Railroad including west of Hudson operations and discussion of CtDOT sponsored rail operations such as Shore Line East and the Springfield to New Haven Hartford Line

Moderators: GirlOnTheTrain, nomis, Jeff Smith

Re: Catenary (Wire) Project Next Phase Fairfield to Bridgepo

Postby Train538 » Mon Apr 28, 2014 8:53 pm

Great news everyone! Track 3 is now back in service between Southport (CP 248) and Bridgeport (CP 255). I presume there are speed restrictions for the rusty rails, right? Now someone needs to get rid of those pesky temporary platforms on track 1 and then my world will be bright and sunny :razz: .
"We have clearance, Clarence. Roger, Roger. What's our vector, Victor? Tower's radio clearance, over! That's Clarence Oveur. Over. Over. Roger. Huh? Roger, over! What? Huh? Who?" (from the movie Airplane!)
User avatar
Train538
 
Posts: 425
Joined: Thu Mar 05, 2009 8:52 pm
Location: Southport, CT

Re: Catenary (Wire) Project Next Phase Fairfield to Bridgepo

Postby fl9m2004 » Mon Apr 28, 2014 8:56 pm

That's really great news
Speaking of wire projects what's up with temporary platforms at east Norwalk on New york bound side
Went by there yesterday they where still up
fl9m2004
 
Posts: 1301
Joined: Thu Apr 11, 2013 10:52 am

Re: Catenary (Wire) Project Next Phase Fairfield to Bridgepo

Postby XBNSFer » Wed May 07, 2014 2:01 pm

If you mean the bridge plates, they were up because of the tie and rail replacement on the movable bridges at Westport and South Norwalk on track 3.
GE, not EMD, makes the best locomotives now; has for over 20 years. Get over it.
XBNSFer
 
Posts: 90
Joined: Fri Aug 06, 2004 9:56 pm
Location: Bridgeport, CT

Final Phase Of Catenary Replacement Project Begins

Postby NH2060 » Fri Sep 05, 2014 2:32 pm

http://newcanaan.dailyvoice.com/news/me ... re-project
Fair use quote:
The end is in sight for Metro-North Railroad as work begins Sept. 6 on the final phase of a massive catenary wire replacement project on the New Haven Line in Connecticut.

Work will begin on two segments -- one from East Norwalk to Greens Farms and another from Bridgeport to Milford. The work will start simultaneously and involve the replacement of about 10.5 miles of catenary along track and in the Bridgeport Yard, Metro-North said in a release.
NH2060
 
Posts: 1442
Joined: Thu Feb 25, 2010 4:44 pm

Re: Final Phase Of Catenary Replacement Project Begins

Postby MACTRAXX » Sat Sep 06, 2014 6:53 am

NH2060: This project is replacing the last of the old New Haven "floating span" catenary
am I right? MACTRAXX
EXPRESS TRAIN TO NEW YORK PENN STATION-NO JAMAICA ON THIS TRAIN-PLEASE STAND CLEAR OF THE CLOSING TRAIN DOORS
MACTRAXX
 
Posts: 3447
Joined: Mon Feb 07, 2005 11:55 am
Location: Islandia,Long Island,NY

Re: Final Phase Of Catenary Replacement Project Begins

Postby Patrick A. » Sat Sep 06, 2014 7:32 am

Spring of 2017 is the estimated completion date according to article, hopefully it holds.
I have lived to ride on the M8.

Complete Constant Tension on the New Haven Line ETC: Mid-2018
Patrick A.
 
Posts: 620
Joined: Thu Jul 06, 2006 8:52 pm
Location: New York, NY

Re: Final Phase Of Catenary Replacement Project Begins

Postby NH2060 » Sat Sep 06, 2014 4:09 pm

MACTRAXX wrote:NH2060: This project is replacing the last of the old New Haven "floating span" catenary
am I right? MACTRAXX

It is indeed. So get your photographs taken now before it's all taken down!
Patrick A. wrote:Spring of 2017 is the estimated completion date according to article, hopefully it holds.

By then it will have been 15+ years since CT began replacing the original 1907 "triangular" catenary and about 25 years since NY started replacing the Pelham-Port Chester section. It sure has taken long enough ;-)
NH2060
 
Posts: 1442
Joined: Thu Feb 25, 2010 4:44 pm

Re: Final Phase Of Catenary Replacement Project Begins

Postby DutchRailnut » Sat Sep 06, 2014 6:04 pm

not much left to photograph the Floating spans are now floating stubs of scrap iron as 3 tracks are already cut off.
If Conductors are in charge, why are they promoted to be Engineer???

Retired Triebfahrzeugführer
User avatar
DutchRailnut
 
Posts: 21200
Joined: Thu Mar 11, 2004 8:02 pm
Location: released from Stalag 13

Re: Final Phase Of Catenary Replacement Project Begins

Postby BuddSilverliner269 » Sun Sep 07, 2014 7:10 pm

I have often criticized MNR about certain things and maybe it sure has taken long to replace the catenary but had it have been any company would it be done any quicker? I think we all know the answer. No.
BuddSilverliner269
 
Posts: 3662
Joined: Wed Jan 18, 2006 2:40 am
Location: Trenton Line MP 30.70

Re: Final Phase Of Catenary Replacement Project Begins

Postby Lackawanna565 » Mon Sep 08, 2014 11:33 am

Once and a great while someone will say that Metro North is destroying railroad history. But of course the old system is kept in place. They will have alot of problems.
User avatar
Lackawanna565
 
Posts: 289
Joined: Mon Jul 31, 2006 11:02 am
Location: Kingston, PA

Re: Final Phase Of Catenary Replacement Project Begins

Postby Tadman » Mon Sep 08, 2014 11:57 am

DutchRailnut wrote:not much left to photograph the Floating spans are now floating stubs of scrap iron as 3 tracks are already cut off.


Not surprising they're scrapping it, but it reminds me - there's a guy in northern Indiana that has an entire yard full of ex-South Shore lattice catenary bridges from 1927. For nostalgia reasons. He also owns an ex-CTA steeple cab, once jokingly referred to here on the forum as the "secret steeple cab" (this was a hot topic maybe 2005-ish). What do you do with stuff like that???
Tadman
 
Posts: 8442
Joined: Wed Sep 01, 2004 10:21 am
Location: Michigan

Re: Final Phase Of Catenary Replacement Project Begins

Postby 7express » Sat Sep 20, 2014 12:47 am

Patrick A. wrote:Spring of 2017 is the estimated completion date according to article, hopefully it holds.



So, we get bridge plates at Bridgeport for the next 2.5 years than?? Beautiful!
7express
 
Posts: 284
Joined: Thu May 06, 2010 12:39 am
Location: New Haven line

Re: Final Phase Of Catenary Replacement Project Begins

Postby DutchRailnut » Sat Sep 20, 2014 7:56 am

We could just leave old catenary and save you the inconvenience ??
If Conductors are in charge, why are they promoted to be Engineer???

Retired Triebfahrzeugführer
User avatar
DutchRailnut
 
Posts: 21200
Joined: Thu Mar 11, 2004 8:02 pm
Location: released from Stalag 13

Track 3 catenary replacement

Postby Saugatuck » Sat Nov 21, 2015 5:43 am

Track 3 has been OOS through Westport and E Norwalk for a while and there doesn't seem to be much activity to reinstall the wire. Anyone have an idea on the ETA for this project?
Saugatuck
 
Posts: 43
Joined: Mon Oct 08, 2012 9:19 pm

Re: Track 3 catenary replacement

Postby Saugatuck » Fri Jan 15, 2016 5:27 pm

Just curious if anyone knows where this project is at this point. Haven't seen any activity, not that that is conclusive evidence there is no progress.
Thanks, Saugs
Saugatuck
 
Posts: 43
Joined: Mon Oct 08, 2012 9:19 pm

PreviousNext