Metro's revised track work & maintenance plan

Discussion related to DC area passenger rail services from Northern Virginia to Baltimore, MD. Includes Light Rail and Baltimore Subway.

Moderators: Robert Paniagua, therock

Re: Metro's revised track work & maintenance plan

Postby JackRussell » Mon Aug 01, 2016 3:20 pm

JDC wrote:Report card for Surge 5, but only up to 7/24. So it does not include the second half of the time, till 7/31. http://www.wmata.com/rail/SafeTrack_Surge5_ProgressReport_v3.pdf?


They noted that traction power work is limited because they need to turn off power to the 3rd rail for both tracks, limiting them to 4-hour work windows. I am wondering whether the derailment indirectly helped them out in that there were no running trains from Friday through Sunday.
JackRussell
 
Posts: 574
Joined: Sun Aug 02, 2009 10:58 am
Location: Northern Virginia

Re: Metro's revised track work & maintenance plan

Postby JDC » Tue Aug 09, 2016 8:05 am

Metro has modified Surge 7 so that on the coming weekend there will be a complete shutdown between Shady Grove and Grosvenor in order to address track/switch issues identified after the recent derailment at EFC. https://www.washingtonpost.com/news/dr-gridlock/wp/2016/08/08/metro-adds-work-to-next-safetrack-project/
Living in Alexandria, Fairfax County; Working at Half & L
User avatar
JDC
 
Posts: 975
Joined: Thu Aug 22, 2013 10:20 am
Location: Fairfax County, VA

Re: Metro's revised track work & maintenance plan

Postby JDC » Tue Aug 09, 2016 8:21 am

Living in Alexandria, Fairfax County; Working at Half & L
User avatar
JDC
 
Posts: 975
Joined: Thu Aug 22, 2013 10:20 am
Location: Fairfax County, VA

Re: Metro's revised track work & maintenance plan

Postby MCL1981 » Tue Aug 09, 2016 9:19 am

How many intense and detailed emergency inspections has Metro conducted this year? I lost count, and that is including the big all-day closure in the spring. And despite numerous intense, detailed, safety focused inspections, this stupid * continues to happen. At some point, leadership and politicians needs to realize that the problem is the people. When you send the same lazy morons that created the problems out to inspect the problems they crated, don't act surprised that nothing changes. The lazy, incompetent, show-up-for-a-check employees that Queen Jackie defends day in and day out are responsible for this. And the managers that allowed it for decades are equally complicate. They could fire thousands of people in all levels of employment and literally nobody would notice them missing. They didn't do crap on the job, and they can continue not doing crap sitting on the street for all I care. At least we'd know nothing's being done, rather than being misled into thinking it's being done. People died because of their laziness.

The only thing that continues to surprise me is that the media and regulators have managed to not notice this for decades until now. It's been obvious to anyone that wanted to see it.
MCL1981
 
Posts: 575
Joined: Sun Nov 11, 2012 9:23 am

Re: Metro's revised track work & maintenance plan

Postby JackRussell » Tue Aug 09, 2016 10:10 am



It is always easy to sit back and criticize - I would be most interested in knowing what the FTA would have done had they had complete say over how things are handled. You get the feeling that they would have been happier with a 6-month total shutdown to conduct repairs, re-training, and firing/hiring. There was so much rot - both in terms of physical condition of the railroad, as well as in the employee base.
JackRussell
 
Posts: 574
Joined: Sun Aug 02, 2009 10:58 am
Location: Northern Virginia

Re: Metro's revised track work & maintenance plan

Postby JDC » Tue Aug 09, 2016 2:47 pm

MCL1981 wrote:How many intense and detailed emergency inspections has Metro conducted this year? I lost count, and that is including the big all-day closure in the spring. And despite numerous intense, detailed, safety focused inspections, this stupid * continues to happen. At some point, leadership and politicians needs to realize that the problem is the people. When you send the same lazy morons that created the problems out to inspect the problems they crated, don't act surprised that nothing changes. The lazy, incompetent, show-up-for-a-check employees that Queen Jackie defends day in and day out are responsible for this. And the managers that allowed it for decades are equally complicate. They could fire thousands of people in all levels of employment and literally nobody would notice them missing. They didn't do crap on the job, and they can continue not doing crap sitting on the street for all I care. At least we'd know nothing's being done, rather than being misled into thinking it's being done. People died because of their laziness.

The only thing that continues to surprise me is that the media and regulators have managed to not notice this for decades until now. It's been obvious to anyone that wanted to see it.



More from the report. https://www.washingtonpost.com/news/dr-gridlock/wp/2016/08/09/7-alarming-findings-in-the-new-fta-report-on-metro-track-maintenance/. The takeaway is that Metro's frontline workers don't know what they're doing in many instances, and their supervisors either don't know- or dont care - to follow Metro's own safety requirements.
Living in Alexandria, Fairfax County; Working at Half & L
User avatar
JDC
 
Posts: 975
Joined: Thu Aug 22, 2013 10:20 am
Location: Fairfax County, VA

Re: Metro's revised track work & maintenance plan

Postby pumpers » Wed Aug 10, 2016 4:31 pm

Here is the link to the full 36-page report: https://tribwdcw.files.wordpress.com/20 ... -08-16.pdf
There are 2 sides to every story, but still .... Some of the items in this report are pretty scary. Hopefully some good will come of it, from politicians to managers to the boots on the ground..
“... FWSO [FTA WMATA Safety Oversight] inspectors found deficient track conditions requiring speed restrictions that were missed by track inspectors, including instances of missing direct fixation or DF fasteners (up to 456 inches between effective DF fasteners) that should have been already noted and repaired. In other instances, questions regarding the cause or source of specific defects, from wheel burns, to spalling and corrosion, were incorrectly identified and the typical progression patterns and timelines for common defects were also not well understood. Many of the track inspectors encountered appeared to be inadequately trained with little or no hands-on-training.”

456 inches? No wonder there are derailments. That's I'm surprised there haven't been more comments here on the report. Guess we are all getting hardened against how bad things can be.
pumpers
 
Posts: 1850
Joined: Mon Oct 25, 2004 1:56 pm

Re: Metro's revised track work & maintenance plan

Postby farecard » Thu Aug 11, 2016 1:25 am

JackRussell wrote:

It is always easy to sit back and criticize - I would be most interested in knowing what the FTA would have done had they had complete say over how things are handled. You get the feeling that they would have been happier with a 6-month total shutdown to conduct repairs, re-training, and firing/hiring. There was so much rot - both in terms of physical condition of the railroad, as well as in the employee base.



What is FTA's history/experience in track inspections?
Where else are they the regulator of rail ops?
User avatar
farecard
 
Posts: 669
Joined: Thu Oct 02, 2008 2:40 am

Re: Metro's revised track work & maintenance plan

Postby JDC » Thu Aug 11, 2016 9:45 am

In order to address these FTA findings, Metro is changing some weekend single tracking into total line shutdowns. For instance, rather than single tracking for Surge 7 this weekend, there will be no service at all between Shady Grove and Grosvenor. https://wamu.org/news/16/08/10/to_get_fixes_done_more_weekend_closures_may_be_coming_to_metro
Living in Alexandria, Fairfax County; Working at Half & L
User avatar
JDC
 
Posts: 975
Joined: Thu Aug 22, 2013 10:20 am
Location: Fairfax County, VA

Re: Metro's revised track work & maintenance plan

Postby JDC » Mon Aug 15, 2016 12:35 pm

Wapo has a really nice story about the failure of metro's overall track maintenance program, including some helpful charts/graphs. https://www.washingtonpost.com/news/dr-gridlock/wp/2016/08/15/metros-track-inspection-program-is-a-mess-and-these-four-graphics-show-why/. Not sure if the track territory one had ever made the rounds before,
Living in Alexandria, Fairfax County; Working at Half & L
User avatar
JDC
 
Posts: 975
Joined: Thu Aug 22, 2013 10:20 am
Location: Fairfax County, VA

Re: Metro's revised track work & maintenance plan

Postby JDC » Tue Aug 16, 2016 6:14 pm

Metro has announced that the current Safe Track plan's surges will be modified in several ways. http://www.wmata.com/about_metro/news/PressReleaseDetail.cfm?ReleaseID=6153. Surge 7, currently underway, will be extended. The surges to follow will occurs on new dates, and Metro will issue a new timeline for surges later in the year/beginning of 2017. The reason for the modification is partly weather - the heat/humidity lately has slowed down surge 7 on the Red line - as well as the FTA's newest safety orders issued to Metro and work on crossovers.
Living in Alexandria, Fairfax County; Working at Half & L
User avatar
JDC
 
Posts: 975
Joined: Thu Aug 22, 2013 10:20 am
Location: Fairfax County, VA

Re: Metro's revised track work & maintenance plan

Postby JDC » Tue Aug 16, 2016 6:20 pm

JDC wrote:In order to address these FTA findings, Metro is changing some weekend single tracking into total line shutdowns. For instance, rather than single tracking for Surge 7 this weekend, there will be no service at all between Shady Grove and Grosvenor. https://wamu.org/news/16/08/10/to_get_fixes_done_more_weekend_closures_may_be_coming_to_metro


A photo Metro put on Twitter of the weekend work on this segment to address the crossover. https://twitter.com/Metrorailinfo/status/765556424357384192
Living in Alexandria, Fairfax County; Working at Half & L
User avatar
JDC
 
Posts: 975
Joined: Thu Aug 22, 2013 10:20 am
Location: Fairfax County, VA

Re: Metro's revised track work & maintenance plan

Postby Sand Box John » Tue Aug 16, 2016 9:48 pm

A light finely came on over somebodies head. The ties under rails in the crossovers of the lesser used interlockings has a service life that is the same as the ties under the mainline rails.
John in the sand box of Maryland's eastern shore.
User avatar
Sand Box John
 
Posts: 2724
Joined: Sun Jan 01, 2006 8:55 pm
Location: Hebron Maryland

Re: Metro's revised track work & maintenance plan

Postby JackRussell » Wed Aug 17, 2016 7:42 am

Sand Box John wrote:A light finely came on over somebodies head. The ties under rails in the crossovers of the lesser used interlockings has a service life that is the same as the ties under the mainline rails.


Give them credit - it only took one derailment for them to figure that one out.
JackRussell
 
Posts: 574
Joined: Sun Aug 02, 2009 10:58 am
Location: Northern Virginia

Re: Metro's revised track work & maintenance plan

Postby JDC » Wed Aug 17, 2016 9:46 am

Metro has posted an interim progress report for surge 7 on the Red Line http://www.wmata.com/Images/Mrel/MF_Uploads/Surge7_Progress_Report_v2.pdf?

It has also created a subpage with photos/videos of the work being done http://www.wmata.com/rider_tools/metro_service_status/advisories.cfm?AID=5728
Living in Alexandria, Fairfax County; Working at Half & L
User avatar
JDC
 
Posts: 975
Joined: Thu Aug 22, 2013 10:20 am
Location: Fairfax County, VA