Last week, at a meeting of the Metropolitan Transportation Authority’s Capital Program Oversight Committee, project executive Bill Goodrich revealed that since February construction delays at the busy Harold Interlocking in Long Island City have been “getting worse.”
The LIRR shares use of the busy rail junction with Amtrak. To carry out work there, East Side Access construction crews rely heavily on Amtrak taking some tracks out of service on specified nights and weekends, and lending some of its workers to the effort.
But despite written agreements with Amtrak detailing their expected cooperation, Goodrich said project workers “have not been receiving the level of support” from Amtrak that the agency has promised.
...
Amtrak spokesman Craig Schulz said the agency “has increased its level of support for East Side Access to help advance the project,” but added that the MTA’s schedule for the project assumes track outages “that go beyond our existing commitments.”
“While the schedule hinges on a number of variables beyond Amtrak’s support, we continue to work closely with MTA to coordinate scheduling and minimize any potential disruption,” Schulz said.
...