Re: Construction and Projects

Postby justalurker66 » Fri Apr 18, 2014 7:04 pm

orangeline wrote:Before moving here I lived in NYC metro area and the subways and elevated portions, with few exceptions, were either constructed outright or modified a long time ago to avoid this kind of traffic interference. I can't help but wonder why the companies that built what became the L didn't do the same on their trunk lines and branches!


A good look at the histories of the lines might help. The Chicago "L" lines once had interurbans and freight trains on their tracks and was built by competing yet cooperating companies. By the time the lines came under the CTA umbrella they were basically bankrupt - with not a lot of money for improvements.

The crossovers work ... and have worked for a long time. The flyover will work better.
User avatar
justalurker66
 
Posts: 2086
Joined: Fri May 15, 2009 11:20 pm

Re: Construction and Projects

Postby orangeline » Sun Apr 20, 2014 10:39 am

orangeline wrote:The Chicago "L" lines once had interurbans and freight trains on their tracks and was built by competing yet cooperating companies. By the time the lines came under the CTA umbrella they were basically bankrupt - with not a lot of money for improvements.


I understand that by the time of CTA things had evolved (devolved?) to where a major reconstruction couldn't happen. I also understand why having flyovers entering the Loop couldn't work. I guess I wonder why when the independent companies were first building the elevateds and adjacent properties weren't as developed they didn't install such features to prevent eventual traffic conflicts as the ridership and number of trains grew.

On the flip side, taking the Northside lines as an example, if they could make it work using just crossovers for local, express, Ravenswood, and North Shore trains operating far greater frequencies, why the need now for a flyover?
"Welcome aboard Orange Line run 711. Travel time to downtown is 25 minutes. Next stop will be Pulaski."
orangeline
 
Posts: 330
Joined: Wed Mar 17, 2004 1:20 pm
Location: LaGrange, IL

Re: Construction and Projects

Postby justalurker66 » Sun Apr 20, 2014 12:31 pm

orangeline wrote:On the flip side, taking the Northside lines as an example, if they could make it work using just crossovers for local, express, Ravenswood, and North Shore trains operating far greater frequencies, why the need now for a flyover?


It may not be needed ... but now is a good opportunity to look at the option (while the rest of Red-Purple is modernized). If they decide not to change Clark Jct the plan will just sit for another 25-50 years (with the rest of the improvements completed).
User avatar
justalurker66
 
Posts: 2086
Joined: Fri May 15, 2009 11:20 pm

Re: Construction and Projects

Postby twropr » Wed May 14, 2014 2:24 pm

The May issue of Metra's BILEVEL briefly mentions a project to renew A-5 interlocking. Is there still an operator controlling this interlocking? What will be accomplished by the project and will more than one track at a time be taken out of service during the work periods?

Andy
Jacksonville, FL
twropr
 
Posts: 609
Joined: Tue Dec 29, 2009 6:26 pm

Re: Construction and Projects

Postby doepack » Wed May 14, 2014 11:03 pm

twropr wrote:The May issue of Metra's BILEVEL briefly mentions a project to renew A-5 interlocking. Is there still an operator controlling this interlocking? What will be accomplished by the project and will more than one track at a time be taken out of service during the work periods?

Andy
Jacksonville, FL



If you haven't done so already, please scroll down a bit in this forum and see topic "A5 project" for more details...
--Dorian--
User avatar
doepack
 
Posts: 2290
Joined: Sat May 07, 2005 5:20 am
Location: UP Geneva Subdivision, MP 25.0

Re: Construction and Projects

Postby twropr » Tue Sep 23, 2014 8:44 pm

Understand that the Englewood Flyover is now in service for midday trains, operating at ?30 MPH while construction continues. Should be fully in service next month.

Andy
twropr
 
Posts: 609
Joined: Tue Dec 29, 2009 6:26 pm

Re: Construction and Projects

Postby Zanperk » Sun Jan 11, 2015 2:03 pm

orangeline wrote: I guess I wonder why when the independent companies were first building the elevateds and adjacent properties weren't as developed they didn't install such features to prevent eventual traffic conflicts as the ridership and number of trains grew.


Hustle up investor cash, make the minimum spend to meet the franchise requirements, and pocket the rest.

In addition, there were two or three generations worth of transit planners convinced that a nice, new subway would replace the inadequate elevated structures. It's only been the last thirty years where the Loop wouldn't be torn down and the lines feeding it replaced by subways.
Zanperk
 
Posts: 90
Joined: Thu Sep 07, 2006 9:59 pm

Re: Construction and Projects

Postby lstone19 » Mon Apr 13, 2015 11:16 am

Only slightly commuter related but over the weekend, a major step in the grade separation of the ex-Milwaukee Road Cut-off at Irving Park Road occurred. From B-17 interlocking, Track 1 now goes to the bridge rather than the ground level track. I don't think it's in-service yet as on Track 2, a new switch provides access to ground-level Track 1 at the west end of B-17. Metra was impacted over the weekend with all ops on Track 2 B-17 to B-12 Saturday while on Sunday, all passenger ops were on Track 1 Roselle to B-12 while I saw a freight from Bensenville yard "wrong-railing" on 2 out to Roselle.
Larry
Roselle, IL (along the MILW West line)
ex-N&W Sandusky, Ohio
lstone19
 
Posts: 669
Joined: Thu Jan 25, 2007 7:40 pm

Re: Construction and Projects

Postby lstone19 » Sat May 02, 2015 7:05 am

And it appears from the state of things (observed from my Metra train home last night) that they are ready to cut Cut-off Track 2 over to the new Irving Park Rd. bridge this weekend.

Now we just need IDOT to do the needed rebuilding of the Irving Park Rd. / York Rd. intersection and we can actually drive under the new bridge (currently closed under the bridge after several trucks ignored low clearance signs and hit it all in the first few hours after the bridge was put in it's final position).
Larry
Roselle, IL (along the MILW West line)
ex-N&W Sandusky, Ohio
lstone19
 
Posts: 669
Joined: Thu Jan 25, 2007 7:40 pm

Re: Construction and Projects

Postby spRocket » Mon May 04, 2015 3:10 pm

lstone19 wrote:Now we just need IDOT to do the needed rebuilding of the Irving Park Rd. / York Rd. intersection and we can actually drive under the new bridge (currently closed under the bridge after several trucks ignored low clearance signs and hit it all in the first few hours after the bridge was put in it's final position).


Someone should set up a webcam at the bridge, like the infamous Gregson St. bridge in Durham, NC. A crash beam had to be installed to protect the bridge.
When it's a tie at the railroad crossing, you lose.
User avatar
spRocket
 
Posts: 60
Joined: Thu Mar 11, 2004 9:44 pm
Location: Mokena, IL

Re: Construction and Projects

Postby byte » Fri Jun 05, 2015 4:50 pm

Work is continuing on the Englewood Flyover - it appears provisions are being provided to allow quadruple-tracking in the near future. The piers holding the new viaduct up are being widened to twice their previous width (on the south side of the structure). Unsure if they'll be putting up a new, parallel viaduct at this time but I suppose it's worth noting that the Metra signage previously mounted on the old bridge has yet to be attached to the new one.
That old car might be worth money!
byte
 
Posts: 1220
Joined: Fri Mar 12, 2004 5:37 pm
Location: IL

Re: Construction and Projects

Postby justalurker66 » Fri Jun 05, 2015 7:04 pm

byte wrote:Work is continuing on the Englewood Flyover - it appears provisions are being provided to allow quadruple-tracking in the near future. The piers holding the new viaduct up are being widened to twice their previous width (on the south side of the structure). Unsure if they'll be putting up a new, parallel viaduct at this time but I suppose it's worth noting that the Metra signage previously mounted on the old bridge has yet to be attached to the new one.

The viaduct was announced as a three track structure.
User avatar
justalurker66
 
Posts: 2086
Joined: Fri May 15, 2009 11:20 pm

Re: Construction and Projects

Postby justalurker66 » Mon Jun 15, 2015 8:16 pm

I took a look this weekend ... the viaducts to the north of the expressway are two tracks on the west bridge, one track on the east bridge (over NS and 63rd St an 61st St). The viaduct immediately south of the expressway is two two track bridges (over Wentworth). I believe the eastern viaduct has not changed
User avatar
justalurker66
 
Posts: 2086
Joined: Fri May 15, 2009 11:20 pm

Re: Construction and Projects

Postby jpIllInoIs » Tue Apr 12, 2016 9:00 am

Cn Freeport construction
I went by the CN at Rt 47 East of Burlington and west of Plato Center.
There was a large project and crew on site to the west of Rt 47.
https://www.google.com/maps/@42.0414326 ... !1e3?hl=en

Any idea of the project scope?
jpIllInoIs
 
Posts: 17
Joined: Mon Feb 15, 2010 9:05 am

Re: Construction and Projects

Postby jpIllInoIs » Wed Apr 13, 2016 6:01 pm

Does anyone know if the BNSF project is complete?
It would be incredible to get some photos of the new construction.

CREATE W4 BNSF Horseshoe http://createprogram.org/factsheets/WA4_2015.pdf

Google Maps https://www.google.com/maps/@41.8374344 ... a=!3m1!1e3
jpIllInoIs
 
Posts: 17
Joined: Mon Feb 15, 2010 9:05 am