Track 5A is completely gone. The switch that lead to it has been removed and the switch configuration there is now different.
EuroStar
 
Posts: 432
Joined: Fri Oct 19, 2012 8:26 pm
Location: Middle of Nowhere

Re: Penn Station Emergency Repairs: Trackwork, etc.

Postby east point » Fri Dec 08, 2017 12:59 pm

How is the ROW for 5A now being used ? Staging for the repair work this winter or for Gateway bores or something else ?
east point
 
Posts: 797
Joined: Tue Feb 16, 2016 1:50 pm

Re: Penn Station Emergency Repairs: Trackwork, etc.

Postby adamj023 » Sat Dec 09, 2017 7:50 pm

Amtrak is running much better since all the work done since this thread was posted. Much less issues with trains from Penn Station. The upcoming work for next month should improve reliability even more as we head to 2018 and hopefully get even better over time as more and more Penn Station related work is completed.

The work on the LIRR Yard in Brooklyn which will be finished as of December, with signals complete will mean LIRR can run more trains without delays to Atlantic Terminal in Brooklyn to bypass Penn Station’s tracks of which Amtrak is working on. This was not yet ready when the previous summer project which took out more tracks was completed. So now future projects in general will be less disruptive at Penn Station and the station will get even better over time as more and more work is performed and finished.

Penn station was IMHO a serious weak link in Amtrak’s network considering it is also the busiest but at least work is going in to deal with it and project schedules are being announced.
adamj023
 
Posts: 134
Joined: Thu Apr 02, 2015 10:03 am

Re: Penn Station Emergency Repairs: Trackwork, etc.

Postby east point » Sun Dec 10, 2017 8:01 pm

adamj023 wrote:
Penn station was IMHO a serious weak link in Amtrak’s network considering it is also the busiest but at least work is going in to deal with it and project schedules are being announced.


Once Wick became aware of the problems he acted very decisively.
east point
 
Posts: 797
Joined: Tue Feb 16, 2016 1:50 pm

Re: Penn Station Emergency Repairs: Trackwork, etc.

Postby Amtrak7 » Sun Dec 10, 2017 9:57 pm

adamj023 wrote:The work on the LIRR Yard in Brooklyn which will be finished as of December, with signals complete will mean LIRR can run more trains without delays to Atlantic Terminal in Brooklyn to bypass Penn Station’s tracks of which Amtrak is working on. This was not yet ready when the previous summer project which took out more tracks was completed. So now future projects in general will be less disruptive at Penn Station and the station will get even better over time as more and more work is performed and finished.


The switch for the new yard lead is going in as we speak, but I have not heard anywhere that the lead itself will go into service this month.
Amtrak7
 
Posts: 2180
Joined: Thu May 01, 2008 4:39 pm
Location: Long Island / Pittsburgh

Re: Penn Station Emergency Repairs: Trackwork, etc.

Postby adamj023 » Sun Dec 10, 2017 11:05 pm

It is scheduled for finishing in December. I believe it will be ready for Monday morning as that is how it seems from LIRR press reports. It was scheduled to be finished earlier than December but got delayed. Next phase is the new platform in Brooklyn in the building before highrise goes up.

Should be faster with more trains running as yard was substantially improved. All publically available information. The Brooklyn yard is an MTA project not Amtrak, but it helps due to tracks taken out of service to reroute trains to Brooklyn instead of Penn Station where Amtrak is responsible for tracks.
adamj023
 
Posts: 134
Joined: Thu Apr 02, 2015 10:03 am

Re: Penn Station Emergency Repairs: Trackwork, etc.

Postby AlKaLI » Wed Jan 10, 2018 11:45 am

Repair work for Track 15 in Penn Station started this past Monday, 1-8-18. Last week, the beginnings of platform barriers between Tracks 15 &16 were being constructed. Monday morning saw the barriers completed. Track 15 is not accessible from the platform. My LIRR commute usually sees my trains enter Penn on Track 16 and leave from 15. Track 15 is OOS. A peek over the barrier ascending the 7th Ave stairway revealed a backhoe on Track 15 and the rails removed. There should be a view from the Track 13/14 platform. I will see if they are removing the concrete as well.
AlKaLI
 
Posts: 175
Joined: Mon Jan 21, 2013 8:08 pm

Re: Penn Station Emergency Repairs: Trackwork, etc.

Postby JamesRR » Thu Jan 11, 2018 9:38 am

Saw this work too this morning, 1/11. The ties have been ripped up and are awaiting disposal. They're moving pretty fast.

I can't recall, but aren't there one or two more tracks that will undergo the same treatment during this project?
User avatar
JamesRR
 
Posts: 289
Joined: Thu Jul 10, 2008 3:31 pm

Re: Penn Station Emergency Repairs: Trackwork, etc.

Postby AlKaLI » Thu Jan 11, 2018 10:15 am

Yes. I believe Tracks 18 & 19 are to be done in this round as well. This work will more affect the LIRR. I hope they are not done at the same time.
AlKaLI
 
Posts: 175
Joined: Mon Jan 21, 2013 8:08 pm

Re: Penn Station Emergency Repairs: Trackwork, etc.

Postby JamesRR » Thu Jan 11, 2018 4:56 pm

Aren't some of those LIRR tracks direct fixation? I know I've peeked down and seen some that appear to be. I wonder if they'll be replaced with traditional half-ties like the rest of the station tracks?
User avatar
JamesRR
 
Posts: 289
Joined: Thu Jul 10, 2008 3:31 pm

Re: Penn Station Emergency Repairs: Trackwork, etc.

Postby east point » Thu Jan 11, 2018 9:29 pm

As the learning curve for the work at NYPS gets higher it may be more work will be done during this work window. That is unless some calamity befalls some where else on Amtrak tracks and the track crews have to be pulled from NYPS.
east point
 
Posts: 797
Joined: Tue Feb 16, 2016 1:50 pm

Re: Penn Station Emergency Repairs: Trackwork, etc.

Postby JamesRR » Tue Jan 16, 2018 10:17 am

Some photos of the track replacement on Track 15 from this past Saturday, 1/13 - taken from the stairway by the Exit Concourse of Track 14:

15_1.jpg
Track bed being cleaned ahead of new track laying.



15_2.jpg
Looking east at demolished track 15



15_3.jpg
Another view of trackbed being cleaned after demo
User avatar
JamesRR
 
Posts: 289
Joined: Thu Jul 10, 2008 3:31 pm

Previous

Return to Amtrak

Who is online

Users browsing this forum: Matt Johnson, mohawkrailfan and 15 guests